Route 46 Expressway - Segment 3

Description: West of the City of Wasco from Kecks Road to Route 33. Convert to a 4-lane expressway. (TCRP #113)

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Kern
City
Zip Code 93249
 
Senate District
16
Assembly District 30
Congressional District 20
 
Caltrans District
06
 
 
County/State Route Kern 46
Postmile Begin/End 7.3 19.8
Project Benefits
 Benefit Baseline Actual
Daily Travel Time Savings (hours)  475    435.6  
Lane Miles Added (Mixed)  26      
Peak Period Time Savings (minutes)  5678    5,204  
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Caltrans Mehran Akhavan (559) 243-3442   mehran.akhavan@dot.ca.gov
Design (PS&E) Phase
Caltrans Mehran Akhavan (559) 243-3442   mehran.akhavan@dot.ca.gov
Right of Way Phase
Caltrans Mehran Akhavan (559) 243-3442   mehran.akhavan@dot.ca.gov
Construction Phase
Caltrans Mehran Akhavan (559) 243-3442   mehran.akhavan@dot.ca.gov
 
Corridor System Management Plan
Caltrans Randy Treece (559) 488-4153   randy.treece@dot.ca.gov
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
RIP Augmentation
$0 $19,970 $19,970
CMIA
$45,000 $-14,625 $30,375
Non-bond Funding
State/Federal*
$34,925 $-19,382 $15,543
Local**
$14,270 $-7,134 $7,136
Non Budgeted ETC
$0 $0 $0
 
Total**** $94,195 $-21,171 $73,024

**** Totals may not add up exactly to column amounts due to rounding

# Approved is planned budget

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
 
Environmental
$450 $-12 $438 $438
Design(PS&E)
$4,795 $-1,216 $3,579 $3,967
Right of Way
$5,230 $6,428 $11,658 $11,355
Construction
$83,720 $-26,371 $57,349 $49,688
 
Total* $94,195 $-21,171 $73,024 $65,449

* Totals may not add up exactly to column amounts due to rounding

** Totals include all actual project funds expenditures. Cost to date expenditure variances are explained in quarterly reports and/or Close-out reports.

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
07/01/2000 

06/14/2005 
 

 
07/01/2000 

06/14/2005 
100  07/01/2000 

06/04/2005 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
01/02/2007 

03/19/2010 
 

 
01/02/2007 

03/19/2010 
100  01/02/2007 

05/03/2010 


-1 
Begin Right of Way Phase

End Right of Way Phase
06/01/2007 

03/19/2010 
 

 
06/01/2007 

03/19/2010 
100  06/01/2007 

04/28/2010 


-1 
Begin Construction Phase

End Construction Phase
07/01/2010 

07/26/2014 
 

 
07/01/2010 

07/26/2014 
100  01/26/2011 

01/16/2013 
-7 

19 
Begin Closeout Phase

End Closeout Phase
07/28/2014 

01/30/2016 
 

 
07/28/2014 

01/30/2016 
100  01/16/2013 

10/30/2014 
19 

15 
Corridor System Management Plan
Adoption Date 09/24/2007    09/24/2007  09/30/2008  -12 
Implementation Date 10/30/2008    10/30/2008  10/30/2008 
????????
Project Benefits
Benefit Baseline Actual
Daily Travel Time Savings (hours) 475 435.6
Lane Miles Added (Mixed) 26
Peak Period Time Savings (minutes) 5678 5,204

Bond Funding Cost
Adopted:
$45,000,000
Current Approved:
$30,375,000
Actual Expenditures:
$30,375,000

 

Status as of December 31, 2023.